Boston BERDO compliance, filed for you
Building Emissions Reduction and Disclosure Ordinance (BERDO 2.0) requires covered buildings in Boston to report energy and water use every year. We gather the data, check it, and file it — usually within a week.
Who’s covered
Non-residential buildings of 20,000 sq ft or more and residential buildings with 15 or more units, plus parcels with several buildings that add up to those sizes.
Annual deadline
May 15 for the previous calendar year. Boston extended the 2026 deadline to August 15 — always check the city’s current date.
Verification
Third-party data verification is required in verification years (for example, 2026 for 2025 data for most buildings).
Penalties
Fines of roughly $150–$300 per violation, which can add up daily (to several thousand dollars a year).
What is Boston BERDO 2.0?
Boston’s Building Emissions Reduction and Disclosure Ordinance (BERDO) began in 2013 as an energy reporting law. In 2021 the city amended it into BERDO 2.0, which keeps annual energy and water reporting and adds greenhouse gas emissions limits that tighten every five years until buildings reach net zero in 2050.
Every covered building has two obligations: report its energy and water use each year through ENERGY STAR Portfolio Manager and the city’s BERDO Reporting Form, and — once its compliance period starts — keep its emissions at or below the limit for its property type. Third-party verification is required in set years.
Larger buildings (35,000+ sq ft or 35+ units) entered emissions compliance in 2025. Smaller covered buildings (20,000–34,999 sq ft or 15–34 units) start in 2030. As an example, offices are limited to 5.3 kg CO₂e per square foot per year from 2025–2029, dropping to 3.2 in 2030.
Key dates
| January–March | Collect calendar-year bills; request aggregated data from Eversource and National Grid |
| May 15 | Annual report due (Portfolio Manager data plus BERDO Reporting Form) |
| 2026 only | Boston extended the deadline to August 15 |
| 2025 | Emissions limits begin for 35,000+ sq ft / 35+ unit buildings |
| 2030 | Emissions limits begin for 20,000–34,999 sq ft / 15–34 unit buildings |
| Every 5 years | Limits tighten (2030, 2035, 2040, 2045) — net zero by 2050 |
The city has moved deadlines in some years. We confirm the current date before every filing.
Is your building covered by BERDO?
BERDO applies to buildings in the City of Boston that are:
- Non-residential buildings of 20,000 sq ft or more.
- Residential buildings with 15 or more units (or 20,000+ sq ft).
- Parcels with two or more buildings that together meet those thresholds.
Each building has a BERDO ID (6 digits) and a Parcel ID (10 digits), which you need to report. For condominium buildings, the condo association or board of trustees is responsible for reporting, verification and emissions compliance.
What to report
All energy and water used by the whole building — including tenant spaces — for January 1 to December 31:
- Electricity — every meter serving the building
- Natural gas
- District steam, hot or chilled water, if you have it
- Delivered fuels (oil, diesel, propane) — all delivery receipts for the year
- On-site solar production, if any
- Water — whole-building water use
Leave out backup generator fuel. Note any meters added or removed during the year.
Good to know
- BERDO sets emissions limits starting in 2025 or 2030 depending on building size, tightening every five years toward net zero in 2050.
- Each building has a 6-digit BERDO ID and a 10-digit Parcel ID — both are needed to report.
- You also complete a separate BERDO Reporting Form in the city’s portal each year.
- Utility data comes from Eversource (electric), National Grid (gas), Vicinity (steam) and Boston Water and Sewer.
What we’ll need from you
- Building address, plus any utility service addresses that differ from it
- Gross floor area for the whole building and each use (office, retail, residential…), number of units and year built
- Your BERDO ID and Parcel ID (we can look it up)
- Utility data for the full calendar year, January 1 – December 31 (usually 13 months of bills)
- If tenants pay their own utilities: whole-building (aggregated) data from the utility, or signed tenant authorization forms
- Access to your ENERGY STAR Portfolio Manager account, if you have one
- Any notice or letter you received from the city
How to comply
- Find your BERDO ID and Parcel IDLook up the building on the city’s BERDO list. Both IDs are required to match your report.
- Set up Portfolio ManagerEnter gross floor area, property uses and details, and add the BERDO ID so the city can match the property.
- Collect whole-building dataRequest aggregated data from Eversource (electric) and National Grid (gas); add Vicinity steam, delivered fuels, solar and Boston Water and Sewer data.
- Check data qualityFix gaps, overlaps and outliers — BERDO fines inaccurate reports separately from late ones.
- Complete third-party verification when dueIn verification years, have a qualified verifier review the data before you submit.
- Submit data and the BERDO Reporting FormShare your Portfolio Manager data through the city’s data request and complete the reporting form in the BERDO portal by May 15.
- Check emissions against your limitCompare your emissions intensity to the limit for your property type and choose a compliance path if you’re over.
Ways to meet BERDO emissions limits
Reduce on-site emissions
Efficiency upgrades and electrification lower emissions from gas and oil. Boston publishes the emissions factors used to calculate your intensity.
Renewable electricity
Enrolling in Boston Community Choice Electricity (Standard or Green 100) or buying qualifying renewable energy certificates can reduce electricity emissions.
Alternative Compliance Payments
Pay $234 per metric ton of CO₂e above your limit into the Equitable Emissions Investment Fund. The rate is reviewed every five years.
Building portfolios
Owners can combine multiple BERDO buildings into a portfolio and comply on a combined basis.
Individual Compliance Schedules
Buildings can apply for a custom emissions schedule based on their own baseline, with Review Board approval.
Hardship compliance plans
Owners facing financial or other hardship can apply for an adjusted plan.
Exemptions and extensions
Boston can grant extensions to reporting deadlines on request — submit the request before the deadline and keep the city’s email approving it. The city has also moved the deadline for all buildings in some years (May 15 became August 15 in 2026).
Emissions flexibility measures — building portfolios, Individual Compliance Schedules, hardship compliance plans and blended limits for mixed-use buildings — each have their own application process and deadlines.
If a building is on the BERDO list in error (for example, it’s below the threshold or was demolished), contact the city to correct it rather than leaving it unfiled.
Common mistakes we fix
- Missing or mistyped BERDO ID, so the city can’t match the Portfolio Manager data to the building
- Submitting Portfolio Manager data but forgetting the separate BERDO Reporting Form
- Leaving tenant-paid electricity out of a building with separately metered tenants
- Missing a third-party verification year, which is a violation even if the report was filed
- Using the wrong property type for a mixed-use building, which changes the emissions limit that applies
- Assuming smaller residential buildings (15–34 units) don’t need to report until 2030 — reporting is annual now; only emissions limits start in 2030
How 1st Green Choice helps
We handle Boston BERDO filings for offices, multifamily rentals, condominium associations, labs, retail and mixed-use buildings. We find your BERDO and Parcel IDs, set up or correct Portfolio Manager, request whole-building data from Eversource and National Grid, complete third-party verification in verification years, and submit both the data and the BERDO Reporting Form.
Once your data is filed, we show you where your building stands against its emissions limit, so you can plan ahead for the next compliance period.
Boston BERDO questions
When is the Boston BERDO deadline?
Which buildings must comply with BERDO?
What are the BERDO penalties?
What is a BERDO Alternative Compliance Payment?
When do BERDO emissions limits start?
When is third-party verification required for BERDO?
Who is responsible for BERDO in a condo building?
Does BERDO include tenant energy use?
Official sources: City of Boston — BERDO · Complying with BERDO emissions standards. Requirements change — we confirm current rules for every filing.