The San José Energy and Water Building Performance Ordinance requires covered buildings to report energy and water use every year. We gather the data, check it, and file it — usually within a week.
Who’s covered
Non-residential and multifamily buildings of 20,000 sq ft or more.
Annual deadline
May 1 for the previous calendar year.
Verification
No routine third-party verification — but the program runs its own data checks, so accuracy still matters.
Penalties
$25 per day (up to $2,500 a year) for buildings under 50,000 sq ft; $50 per day (up to $5,000 a year) for larger buildings.
What is San José’s Building Performance Ordinance?
San José adopted its Energy and Water Building Performance Ordinance (BPO), Chapter 17.85 of the city code, in December 2018. It has two parts:
- Annual benchmarking: buildings of 20,000 sq ft or more report a full year of energy and water use through ENERGY STAR Portfolio Manager by May 1.
- Beyond Benchmarking: every five years, on a schedule set by parcel number, each building must show it already performs efficiently — or complete improvement actions such as an energy and water audit, retro-commissioning or efficiency measures, carried out by a licensed Qualified Professional.
Complying with the BPO also satisfies the state’s AB 802 for the same building.
Key dates
| May 1 | Annual energy and water benchmarking report due |
| May 1 (your cycle year) | Beyond Benchmarking compliance for buildings on that year’s list |
| Up to 180 days | Extension available for Beyond Benchmarking, if requested by May 1 |
| Every 5 years | Beyond Benchmarking repeats on the building’s cycle |
We confirm your Beyond Benchmarking year with the city before every filing.
Is your building covered?
The BPO covers privately owned commercial and multifamily buildings of 20,000 sq ft or more in San José, and city-owned buildings of 15,000 sq ft or more. Exclusively industrially zoned buildings are exempt from some requirements, and some residential buildings are exempt from water requirements.
The city publishes an annual list of buildings due for Beyond Benchmarking, by parcel number (APN) and San José Building ID.
What to report
All energy and water used by the whole building — including tenant spaces — for January 1 to December 31:
- Electricity — every meter serving the building
- Natural gas
- District steam, hot or chilled water, if you have it
- Delivered fuels (oil, diesel, propane) — all delivery receipts for the year
- On-site solar production, if any
- Water — whole-building water use
Leave out backup generator fuel. Note any meters added or removed during the year.
Good to know
- Buildings that don’t meet the city’s performance standards need an energy audit or retro-commissioning every five years.
- Buildings that report to San José don’t file separately under California’s AB 802.
What we’ll need from you
- Building address, plus any utility service addresses that differ from it
- Gross floor area for the whole building and each use (office, retail, residential…), number of units and year built
- Your San José Building ID (we can look it up)
- Utility data for the full calendar year, January 1 – December 31 (usually 13 months of bills)
- If tenants pay their own utilities: whole-building (aggregated) data from the utility, or signed tenant authorization forms
- Access to your ENERGY STAR Portfolio Manager account, if you have one
- Any notice or letter you received about this law
How to comply
- Confirm your Building ID and cycle yearCheck the city’s benchmarking and Beyond Benchmarking lists.
- Benchmark energy and waterEnter a full calendar year of whole-building data in Portfolio Manager, including water from your water retailer.
- Collect whole-building dataRequest aggregated data from PG&E and San José Clean Energy.
- Submit by May 1Report through the city’s Portfolio Manager data request.
- Complete Beyond Benchmarking in your yearChoose the performance pathway or the improvement pathway for energy and for water, and have a Qualified Professional complete the work.
Beyond Benchmarking pathways
Performance pathway
Show the building already meets efficiency standards for energy and water — for example, with a strong ENERGY STAR score or verified improvement.
Improvement pathway
Complete an audit, retro-commissioning or at least two efficiency improvement measures per utility type.
Qualified Professional
All Beyond Benchmarking work must be completed by a licensed Qualified Professional.
Exemptions and extensions
Owners can request a Beyond Benchmarking extension of up to 180 days by filing the city’s extension form no later than May 1 of the compliance year. Exemptions are available in limited circumstances through the city’s exemption request form.
The city notes that annual benchmarking doesn’t require hiring a vendor — but Beyond Benchmarking does require a licensed professional. Failure to comply can bring fines.
Common mistakes we fix
- Leaving out water, which San José requires
- Missing a Beyond Benchmarking year tied to the parcel number
- Requesting an extension after May 1
- Using a professional who isn’t qualified under the ordinance
- Filing with the state separately when the BPO already covers AB 802
How 1st Green Choice helps
We file San José energy and water benchmarking, request aggregated data from PG&E and San José Clean Energy, and track your Beyond Benchmarking year. When it’s due, our in-house PEs determine whether your building can use the performance pathway — and coordinate the improvement pathway if not.
Related laws and services
San José BPO questions
When is the San José benchmarking deadline?
Which buildings are covered by the San José BPO?
What is Beyond Benchmarking?
How do I know my Beyond Benchmarking year?
Can I get an extension?
Is water required?
Does the BPO satisfy AB 802?
Who can do Beyond Benchmarking work?
Official sources: City of San José — Building Performance Ordinance · San José — Beyond Benchmarking. Requirements change — we confirm current rules for every filing.